Below is the fee schedule for various engineering related activites as established by City Ordinance.
| Ordinance | Fee | Amount | ||
| 1044.04m | Sewer Tap-in | $1500 per equivalent single family home (see table) | ||
| 1044.04b | Sewer Inspection - residential and commercial | $100 per first 2 hours. City's ragte thereafter | ||
| 1040.01 | Water Tap | Inside City | Outside City | |
| New 3/4" service | $385 | $423.50 | ||
| New 1" service | $440 | $484 | ||
| New 1 1/2" service | $660 | $726 | ||
| New 2" service | $770 | $847 | ||
| Water meters | Inside City | Outside City | ||
| 5/8" | $140 | $154 | ||
| 3/4" | $140 | $154 | ||
| 1" | $170 | $187 | ||
| 1 1/2" | $330 | $363 | ||
| 2" | $420 | $462 | ||
| 2005-130 | Water Inspection | $100 per first 2 hours. City's rate thereafter | ||
| Numerous | Water and Sewer contract line fees and unrecorded assessments | Varies, depending on location | ||
| 2007-07 | Water and Sewer tapper licensing fee | $10,000 performance bond. $100 per license year. | ||
| 2005-129 | Storm Permit | $100 per address | ||
| 1020.02 | Roadway work permit | No charge at this time. Possible bond and inspection costs. | ||
| 1040.03 | Geothermal well fee | $125 per well plus $25 per year. | ||
| 1220.06 | Planning Commission application | $100 | ||
| 1220.05 | Special professional services | Varies | ||
| 2006-133 | Site plan review fee | $100 for residential and 2-family. 1% of site work cost with $100 minimum for others. | ||
| Copying costs | $.25 per copy page. $1.00 per plan sheet. | |||
| Subdivisions, Roadway and Utility Extensions. | ||||
| 1220.06 | Plan review | Up to $3000 | ||
| 1242.02 | Plat approval | $25 minimum, based on number of lots, curved boundaries, etc. | ||
| 1246.13 | Bond, escrow account, of letter of credit | 100% of cost of public improvements. | ||
| 1246.13 | Inspection cost | City's cost. Minimum 2% of construction. No maximum. | ||
| 1020.05 | Right-of-way vacations. | Legal filing, Engineering and Finance Director's time. | ||
| Industrial Buildings | ||||
| 1044.08c | Pretreatment system for any process waste (as designed by applicant's engineer) | $200 application fee. | ||
| 1044.09 | Pretreatment system monthly charge | Revised yearly based on City's costs. | ||
| 1046.10 | Extra-strength waste surcharge | Revised yearly. | ||